16.09 : Matrix Illuminated!  Beautiful!  Bad spots identified and fixed.
 
 16.09 : Electronics Refactored.
 
 16.09 : Event announcement sent.  Flyers made by Maja!
 
 16.09 : Camera mounted!
 
 16.09 : Video tested!  Beautiful Image.  (Thank you,  RF Concepts )
 
 16.09 : Main room enclosure hangs.
 
 15.09 : Basic-X display program tested.
 
 15.09 : Serial indexing of bright LEDs fixed.
 
 15.09 : Sound Space Implemented
 
 14.09 : Floor Textile Partial Suspension Test Underway
 
 13.09 : Sky Hung under tension.
 
 12.09 : Consolidating basic-x display programs.
 
 12.09 : Serious floor hardware mounting by Lina and Gert.
 
 12.09 : Completed wiring of matrix.
 
 11.09 : Constellation wiki up.
 
 11.09 : Constellation Invitation Sent.
 
 11.09 : Event announcement up.
 
 11.09 : Solder matrix.
 
 11.09 : Attach floor mounting hardware.
 
 10.09 : Test frame stability.  Consultation with Gert on Construction.  Contract Gert to mount support hardware on walls.
 
 10.09 : Floor Bladders Arrived.  Consulted with delivery person, Toure, who is studying communications.  He would like to help us.
 
 09.09 : Reconsidering sound system 
spec due to budget.
 
 
 08.09 : LED Matrix Undergoing Physical Construction.
 
 08.09 : The Bright LEDs are now here!!
 
 08.09 : Open Constellation Design Initiative Begun.
 
 08.09 : LED control from BasicX successful!!
 
 08.09 : Tensile Floor Textile Construction Begun by Lina!!!
 
 08.09 : More Floor Textile+Water Prototyping.
 
 07.09 : More Spirited Discussion of the LED Mesh Structure!
 
 07.09 : Work with LED controller software.
 
 07.09 : Work on Fabric Floor
 
- 
 
 07.09 : Consultations with Lina and Gert on LED mesh structure.
 
 06.09 : Established details (date, time, audience) regarding public exhibition at and with   FoAM
 
 05.09 : Serial data transmission from Max to Basic-X successful!!!!!
 
 05.09 : Obtained most remaining electronics
 
 05.09 : LEDs Deliverable Monday
 
 05.09 : Liquid Floor Ordered.  Deliverable Monday.
 
 05.09 : Rescale project to 6m x 6m, reducing floor cost by 40%.
 
 05.09 : Began Testing Serial Communication Capability of BasicX
 
 05.09 : LED Controllers arrived
 
 04.09 : unlocked (used hardware reset to remove interrupt loop)
 
 04.09 : Liquid Floor Component Tested.